PROMISE Project facts

Coordinator
Fundacion Tecnalia Research & Innovation
Start date
1 January 2025
End date
31 August 2028
Duration
44 months
Topic
Quantum sensing and metrology for market uptake
Type of Action
Innovation Action (IA)

PROMISE Work packages

Work package 1

Requirements and specifications

Define material, component, and system specifications to ensure comparable measurements and meet use case requirements.

Work package 2

Instrument development

Design a compact optical and mechanical system for sample and diamond integration, and develop tailored SPAD and microwave components to meet performance requirements.

Work package 3

Diamond development

Develop and provide CVD-grown diamond membranes (<100 μm) with activated NV centres, optimizing thickness, nitrogen concentration, and crystal orientation ((100), (111), (110)).

Work package 4

Prototypes assembly and integration

Assemble widefield magnetometers tailored for graphene and corrosion analysis, as well as magnetic material characterization and tumor cell identification.

Work package 5

Use cases

Use cases: Acquire high-resolution images to analyze defects in graphene, corrosion and cracks in metals, magnetic quality control in micromagnets, and intracellular changes to distinguish tumor from non-tumor cells.

Work package 6

Machine learning for quantum image analysis

Development of a data processing suite for widefield imaging magnetometers with tailor-made routines to automate measurement, evaluation, and detection of target variables.

Work package 7

Standardization

Contribution to CEN/CLC JTC-22 WG2 by the consortium representative, focusing on standardizing measurements, components, and the data format for magneto-imaging.

Work package 8

Communication, dissemination and exploitation

Increase public awareness of NV-based quantum sensors, maximize the consortium's impact through IPR monitoring and exploitation plans, and develop industrialization and commercialization roadmaps for PROMISE prototypes to ensure early market adoption.

Work package 9

Project management and coordination

Coordination of participant actions, progress monitoring for project goals, administrative management, and providing a reliable interface to EC services.

PROMISE Timeline

January 1th 2025

M1

Kick-off meeting

March 31st 2025

M3

Use case requirements gathered to delimit the system specifications.

February 28th 2026

M14

Instrument components ready for integration

August 30th 2026

M20

First versions of prototypes ready

February 28th 2027

M26

First imaging reports with procedures for all use cases

February 29th 2028

M38

Final prototypes ready for validation.

August 31st 2028

M44

Final results of the PROMISE project with exploitation and commercialization routes selected